Sikafloor®-263 SL CN
2-part epoxy self smoothing screed and broadcast system
Sikafloor®-263 SL CN is a two part multi purpose binder based on epoxy resin for highly filled self-smoothing screeds.
- Good chemical and mechanical resistance
- Easy application
- Economical
- Solvent-free
- Slip resistant surface possible
Usage
- For self smoothing layers on concrete and cement screeds with normal up to medium heavy wear e.g. storage and assembly halls, maintenance workshops, garages and loading ramps etc.
- The broadcast system is recommended for wet process area, e.g. in beverage industry, food processing, maintenance hangars etc.
Advantages
- Good chemical and mechanical resistance
- Easy application
- Economical
- Solvent-free
- Slip resistant surface possible
Packaging
Part A | 20.8 kg/pail |
Part B | 5.2 kg/pail |
Colour
Part A | Coloured liquid |
Part B | Yellowish transparerent liquid |
Product Details
APPROVALS / CERTIFICATES
Meet the requirements of GB/T 22374-2018
Composition
Epoxy
Shelf life
24 months
Storage conditions
Stored properly in original, unopened and undamaged sealed packaging in dry conditions at temperatures between +5°C and +30°C.
Density
Part A | ~1.6 kg/l |
Part B | ~1.0 kg/l |
Mixed resin | ~1.4 kg/l |
All Density values at +23°C.
Solid content by mass
~100%
Solid content by volume
~100%
Volatile organic compound (VOC) content
< 60g/l | GB/T 22374-2018 |
Shore D Hardness
~76 | GB/T 22374-2018 |
Abrasion resistance
~20 mg | GB/T 22374-2018 |
Compressive strength
~60 N/mm2 | GB/T 22374-2018 |
Tensile adhesion strength
~4.5 N/mm2 | GB/T 22374-2018 |
Temperature resistance
Exposure* | Dry heat |
Permanent | +50°C |
Short-term max. 7 d | +80°C |
Short-term max. 12 h | +100°C |
Short-term moist/wet heat* up to +80°C where exposure is only occasional
(steam cleaning etc.)
*No simultaneous chemical and mechanical exposure.
Chemical resistance
Resistant to many chemicals. Please ask for a detailed chemical resistance table.
Application
Mixing ratio
Part A : Part B = 4 : 1 (by weight)
Ambient air temperature
+10°C min. / +30°C max.
Relative air humidity
80% r.h. max.
Dew point
Beware of condensation!
The substrate and uncured floor must be at least 3°C above dew point to reduce the risk of condensation or blooming on the floor finish.
Substrate temperature
+10°C min. / +30°C max.
Substrate moisture content
< 4% pbw moisture content.
Test method: Sika®-Tramex meter or CM - measurement.
No rising moisture according to ASTM (Polyethylene-sheet).
Pot Life
Temperatures | Time |
+10°C | ~ 50 minutes |
+20°C | ~ 25 minutes |
+30°C | ~ 15 minutes |
Waiting time to overcoating
* Before applying Sikafloor®-263 SL CN on Sikafloor®-161 L allow:
Substrate temperature | Minimum | Maximum |
+10°C | 24 hours | 3 days |
+20°C | 12 hours | 2 days |
+30°C | 8 hours | 1 day |
Times are approximate and will be affected by changing ambient conditions particularly temperature and relative humidity.
Applied product ready for use
Temperature | Foot traffic | Light traffic | Full cure |
+10°C | ~ 30 hours | ~ 6 days | ~ 10 days |
+20°C | ~ 24 hours | ~ 3 days | ~ 7 days |
+30°C | ~ 16 hours | ~ 2 days | ~ 5 days |
Note: Times are approximate and will be affected by changing ambient conditions.
Consumption
System | Product | Consumption |
Primer | Sikafloor®-161 L | 0.35 - 0.55 kg/m² |
Levelling (optional) | Sikafloor®-161 L leveling mortar | Refer to PDS of Sikafloor®-161 L |
Self-smoothing wearing course (Film thickness ~ 1.5 - 3.0 mm ) | 1 pbw Sikafloor®-263 SL CN 0.7 pbw quartz sand (Sikadur® 505 Q) | 1.75 kg/m² mixture /mm thickness Filler quantity depended on temperature and filler type |
Broadcast system (Film thickness ~ 4.0 mm) | 1 pbw Sikafloor®-263 SL CN 1 pbw quartz sand (Sikadur® 505 Q) + broadcasting quartz sand 0.4 -0.7 mm + Seal coat Sikafloor®-263 SL CN | 2.00 kg/m² 2.00 kg/m² ~ 4.0 kg/m² ~ 0.7 kg/m² |
These figures are theoretical and do not allow for any additional material due to surface porosity, surface profile, variations in level and wastage etc.
The quantity of quartz sand in self-leveling system based on the temperature of ambient and substrate approx. 23℃ and 2mm thickness. The actual addition of quartz sand should be depending on temperature and thickness on site, higher temperature and thickness, more quantity of quartz sand can be added in to resin mixture.
EQUIPMENT
Sikafloor®-263 SL CN must be mechanically mixed using an electric power stirrer (300 - 400 rpm) or other suitable equipment.
MIXING
Prior to mixing stir part A mechanically. When all of part B has been added to part A, continuously mix for 2 minutes until a uniform mix has been achieved.
When parts A and B have been mixed, the quartz sand 0.1 - 0.3 mm and/or Extender T must be mixed with part A and B for a further 2 minutes until a uniform mix has been achieved.
To ensure thorough mixing pour materials into another container and mix again to achieve a consistent mix.
Over mixing must be avoided to minimize air entrainment.
CLEANING OF EQUIPMENT
Clean all tools and application equipment with Thinner C immediately after use. Hardened / cured material can only be mechanically removed.
CLEANING
To maintain the appearance of the floor after application, Sikafloor®-263 SL CN must have all spillages removed immediately and must be regularly cleaned using rotary brush, mechanical scrubbers, scrubber dryer, high pressure washer, wash and vacuum techniques etc. using suitable detergents and waxes.